Beverly Power Line Rd

ProjectBeverly Power Line Rd
Duration5 Months
LocationFlinders Ranges, SA
Sector
Services

Works included top soil stripping, clay subgrade formation and survey.

SCOPE OF WORKS

  • Sub base construction – 230mm layer of base course rubble.
  • Capping layer construction- 100mm layer of calcrete material.
  • All design levels were controlled using our GPS machine control 12M Grader.
  • Laying of 400m of RCBC, 250m of 600mm welded poly pipe
  • Onsite crushing of 30,000 tonnes of calcrete material
  • D9T Bulldozer used for raising rock; material was transported using road train side tippers
  • This project was delivered on a 7 day a week program, operators and supervisors were rotated on a 2 on 2 off roster,
  • Company aircraft was utilised for all shift change flights to and from site.